User Guide
Calculate RPW helps industrial engineers, operations students, and manufacturing teams balance assembly lines by grouping tasks into workstations without exceeding a target cycle time.
Key Terms
- Node: A numbered work element in your assembly sequence (1, 2, 3, and so on).
- Tek: Time required to finish a single work element (zero or positive).
- Precedence Edge (
From -> To): Dependency showing that theFromtask must finish before theTotask starts. - Final Node: Terminal task where all precedence paths converge.
- Cycle Time: Maximum allowed workload per workstation.
- RPW (Ranked Positional Weight): Sum of a task's own
Tekplus theTekof every downstream task reachable from it. - Balance Delay: Idle fraction across all stations relative to total station capacity.
- Production Rate: Output rate given by
1 / maxStationLoadunits per minute.
Guided Form Mode
- Select Guided Form at the top of the calculator (or choose a preset from Quick Examples).
- Enter From, To, and the From node's Tek, then select Add.
- Enter the Final Node, Final Tek, and target Cycle Time.
- Select Calculate to generate workstation assignments, RPW rankings, arrow chains, and efficiency metrics.
- Tap any result card to copy that entry, or select Copy Report to copy the full summary.
Quick Text Mode
Switch to Quick Text for keyboard-driven entry with spaces:
- Enter total number of connections (for example
6). - Enter each connection as
From To Tek(for example1 2 0.4). - Enter
FinalNode Tek(for example6 0.4). - Enter
CycleTime(for example1.0). Calculation starts automatically after step 4.
Worked 6-Node Example
- Edges:
1 2 0.4,1 3 0.4,2 4 0.6,3 4 0.3,4 5 0.5,5 6 0.2 - Final node and Tek:
6 0.4 - Cycle time:
1.0 - Balanced output:
- Station 1:
N1, N2(Load1.0, Idle0) - Station 2:
N3, N4, N5(Load1.0, Idle0) - Station 3:
N6(Load0.4, Idle0.6) - Balance Delay:
20%(0.2), Line Efficiency:80%, Production Rate:1 units/min